Press release

Ailes Marines has selected Saipem for the transport and installation of the "jacket" type foundations for the Saint-Brieuc offshore wind farm substation.

Saint-Brieuc / Paris - July 22, 2020 - Ailes Marines, an Iberdrola Group company in charge of the development, construction, installation and operation of the offshore wind farm in the Bay of Saint-Brieuc, has selected Saipem to transport and install the "jacket" type foundations and the upper part of the offshore substation.
The installation works will be carried out using the Saipem 7000, a heavy lift vessel, while project management and engineering activities will be carried out by Saipem SA, its French branch operating throughout the territory.

22

July

20

Saint-Brieuc offshore wind farm

The Saint-Brieuc offshore wind farm will be built in the bay of Saint-Brieuc in Brittany, 16.3 kilometres off the French coast. When completed, the 496 MW wind farm will produce 1,820 GWh per year, equivalent to the annual electricity consumption of 835,000 inhabitants. The installation of the power substation will take several months in 2022. The wind farm will be fully operational in 2023.

"This cutting-edge project, which we are carrying out alongside Ailes Marines, will facilitate the energy transition in France. Thanks to our unique engineering know-how and world-class construction vessels, such as the Saipem 7000, this contract will allow us to reaffirm our leadership and commitment to the renewable energy industry in Europe".

Guido D'Aloisio

Director of Saipem's new Offshore Renewable Energy Unit

"The signing of this contract is a strong signal of Iberdrola's commitment to industrial jobs in France and, more generally, to the green transition in Europe. The offshore wind project in the Bay of Saint-Brieuc, a strategic element of the energy transition in France, will soon begin its construction phase, in consultation with local stakeholders".

Javier Garcia Perez

President of Ailes Marines and International Offshore Director of Iberdrola

logo-ailes-marines-baseline-blue

About Ailes Marines

Winner of a national tender with the Baie de Saint-Brieuc offshore wind farm project, AILES MARINES is in charge of the development, construction, installation and operation of the offshore wind farm. It is a simplified joint stock company (SAS), 100% owned by IBERDROLA Key figures for the Baie de Saint-Brieuc offshore wind project: - 75 km2 area - 62 Siemens Gamesa SG 8.0-167 DD wind turbines, of 8 MW unit capacity - 496 MW installed capacity - 1,820 GWh/year output, equivalent to the annual electricity consumption of 835,000 inhabitants (including heating) All information concerning the Saint-Brieuc offshore wind farm project developed by the company Ailes Marines is available on the website https://ailes-marines.bzh/ You can follow Ailes Marines news on twitter @AilesMarines

  • 75 km2 in area
  • 62 8 MW Siemens-Gamesa wind turbines
  • 496 MW of installed capacity
  • 1,820 GWh/year of production, i.e. the annual electricity consumption of 835,000 inhabitants (including heating)
GE Grid Solutions

About Saipem

Saipem is a leading company specializing in engineering, drilling and construction of major energy and infrastructure projects. It is a company organized in five distinct branches (Offshore E&C, Onshore E&C, Offshore Drilling, Onshore Drilling and XSIGHT, dedicated to conceptual design). Saipem is a global solutions provider, with unique expertise and skills, as well as state-of-the-art technologies that enable it to identify innovative solutions to meet its customers' expectations. Listed on the Milan Stock Exchange, the company is present in more than 70 countries around the world and employs 35,000 people of 120 different nationalities.

  • Press contact: Saipem
    Email: media.relations@saipem.com Switchboard: +39 0244231
symorg-logo-contact

Press Relations & Communication

Jean Christophe Labastugue
Manager

All Press Releases

July 06 2023

France's second offshore wind farm produces its first green megawatt-hours in Brittany

Ailes Marines, a company 100% owned by the Iberdrola group, today announces the production of the first megawatt-hours from the Saint-Brieuc offshore wind farm. The Iberdrola Group launches production of its first French offshore wind farm, and the 4th in Europe. The commissioning confirms the Group's leading position in this business segment. For the first time in Brittany, electricity is being generated by an offshore wind farm. Since July 05, the electrons generated by the wind turbines have been fed into the national grid by RTE. The wind farm's output will...
May 12 2023

Ailes Marines, a subsidiary of Iberdrola, has installed the first offshore wind turbine in Brittany.

The installation of the first of the 62 wind turbines that will equip the Saint-Brieuc wind farm was carried out on May 9 by Ailes Marines' contractor, Siemens Gamesa Renewable Energy. The operation was carried out from the Norwegian company Fred Olsen's jack-up vessel Brave Tern.
Mar 27 2023

Resumption of drilling and installation work on the wind farm in the Bay of Saint-Brieuc.

Ailes Marines announces today the resumption of drilling and installation work on the wind farm in Saint-Brieuc Bay. These operations will mobilize up to thirty vessels for several months. During this period, the rules of navigation and maritime safety are set by prefectural orders.
Tue 03 2023

Pioneering environmental studies recognized by the international scientific community

PLos One and Limnology & Oceanography Methods, two international scientific publications, have validated the protocols for measuring the effects of noise on scallops. These measurements were carried out by independent scientists before and during the installation of the components of the offshore wind farm in the Bay of Saint-Brieuc. The campaign of noise monitoring measurements on scallops represents a world first for marine biology research.
Tue 02 2023

Ailes Marines, a subsidiary of Iberdrola, inaugurates the temporary technical base of the Saint-Brieuc offshore wind farm in the port of Saint-Malo

The temporary technical base of the Saint-Brieuc offshore wind farm was inaugurated on Friday, February 24, 2023 by Daniel Cueff, Vice-President of the Brittany Region and Stéphane Alain Riou, Director of Offshore Wind Iberdrola France in the port of Saint-Malo. The maintenance operations of the wind farm will be carried out temporarily from this base with the vessel EDDA Goëlo.
Dec 20 2022

Signing of a partnership to study the feasibility of a sustainable and integrated aquaculture farm within the Saint-Brieuc offshore wind farm.

Ailes Marines, a company wholly owned by the Iberdrola group, and the Comité Régional de la Conchyliculture Bretagne Nord (CRCBN) signed today an agreement to finance a feasibility study for an Integrated Multi-Trophic Aquaculture (IMTA) farm project.
July 08 2022

The electrical substation of the Saint-Brieuc offshore wind farm has been successfully installed

Saipem has installed the first offshore electrical substation in Brittany. This is the second substation installed on an offshore wind farm in France.
Jul 05 2022

The first foundation for the Saint-Brieuc offshore wind farm has been successfully installed

Ailes Marines announces today the successful installation of the first jacket foundation of the 62 wind turbines of the Saint-Brieuc offshore wind farm.
July 01 2022

Installation of the first foundation for the Saint-Brieuc offshore wind farm

Press release Installation of the first foundation of the Saint-Brieuc offshore wind farm Pleudaniel / Lézardrieux / Saint-Brieuc / Paris - 01 July 2022 - Ailes Marines, a company wholly owned by the Iberdrola group, today announced the start of the installation of the first jacket foundation of the 62 wind turbines of the offshore wind farm in the Bay of Saint-Brieuc This installation phase will involve 5 vessels in the area. The navigation and maritime safety rules are set by prefectural decrees. During this phase of work, Ailes Marines is continuing to take measures to protect the...
Tue 07 2022

Construction work resumes on the Saint-Brieuc offshore wind farm

Ailes Marines announces today the resumption of construction work on the wind farm in the Bay of Saint-Brieuc. The Van Oord vessel Aeolus, which is responsible for installing the piles and foundations of the wind turbines, will be working in the area without interruption in 2022 and 2023. The wind farm will be delivered at the end of 2023
Nov 01 2021

Fin de la première phase des travaux en mer du parc éolien de Saint-Brieuc

Lézardrieux / Saint-Brieuc / Paris – Le 31 octobre 2021 – Ailes Marines annonce aujourd’hui la fin de la première phase des travaux de construction pour l’année 2021. Les opérations sont totalement achevées, le navire AEOLUS est prêt à quitter la zone. Il est en attente d’une fenêtre météo favorable pour son retour en flottaison, afin de rejoindre son port d’attache. Les travaux de construction en mer du parc reprendront le 1er mars 2022 au plus tard.
August 18 2021

Ailes Marines re-establishes the truth against false information about the Saint-Brieuc offshore wind farm

Following numerous affirmations and untruths relayed in recent weeks by media, Ailes Marines would like to provide once again details and clarifications about the Saint-Brieuc offshore wind farm.
August 13 2021

The 2021 inter-array cable pre-trenching campaign is now completed

Ailes Marines announces the end of the pre-trenching campaign for inter-array cable routes. The Aethra vessel leaves the work area today almost 5 weeks ahead of schedule. Drilling work is continuing on the northern zone of the park.
July 31 2021

AEOLUS vessel resumption to drilling work

Ailes Marines conducted several helicopter overflights of the area and nautical patrols. These control operations were carried out considering the modeling provided by the Documentation Center for Research and Experimentation on Accidental Water Pollution (CEDRE).
July 28 2021

Processing a drilling rig incident on the AEOLUS vessel

An incident was reported this morning by the captain of the ship AEOLUS to the CROSS Corsen (Regional Operational Center for Surveillance and Rescue) and the maritime coordination of Ailes Marines (MCC).
During the series of drillings on position SB57, a technical problem was observed on one of the ship's three drills. Upon learning of the incident, Van Oord halted all ongoing drilling activities on the AEOLUS and decided to reassemble the affected drill. During the ascent of the tool, a hydraulic fluid of the "PANOLIN HLP SYNTH 46" type was observed on the deck of the AEOLUS vessel and in the marine environment.
July 15 2021

Resumption of drilling work on the Saint-Brieuc offshore wind farm

Lézardrieux / Saint-Brieuc / Paris – July 15, 2021 – Ailes Marines announces the return of the AEOLUS to the area from July 16, 2021, following the agreement of the maritime authorities. The jack-up vessel of the Van Oord company is responsible for drilling and installing the foundation piles for the offshore wind farm. After a complete review of the vessel's tools and equipment carried out by Van Oord in the Netherlands, all of the work control and monitoring protocols have been reassessed. Ailes Marines also announces the signing of an agreement with CEDRE.
June 16 2021

Ailes Marines provides details on the incident of 14 June 2021

The jack up vessel AEOLUS, operated by the company Van Oord, in charge of drilling operations and foundation piles installation for the offshore wind farm, left the Bay of Saint-Brieuc today for its harbour in the Netherlands (Vlissingen), a decision that was approved by the authorities. In parallel, Ailes Marines confirmeds the continuation of the pre-trenching activities currently underway on the site, carried out by the company Prysmian with the vessel AETHRA.
June 15 2021

Immobilisation of the vessel AEOLUS for tooling verification

The jack up vessel AEOLUS, in charge of drilling operation and foundation piles installation for Saint-Brieuc offshore wind farm has currently halted operations on site. This decision was taken following a technical problem encountered during the second cycle of drilling. This technical problem resulted in the leakage of Panolin HLP SYNTH hydraulic fluid used in the drill template guidance systems.
Apr 28 2021

Renforcement des suivis environnementaux pendant les travaux de forage

Durant la première phase des travaux de forage qui se déroule de mai à octobre 2021 sur la zone nord du périmètre du parc de Saint-Brieuc, Ailes Marines instaure des mesures renforcées de suivis en temps réel sur le bruit et la turbidité (état trouble de l’eau). Des mesures de contrôle renforcées de la turbidité – Des mesures de suivis renforcées de bruit – De nouvelles mesures complémentaires.
Apr 21 2021

Démarrage de la construction du parc éolien en mer de Saint-Brieuc

Ailes Marine confirme aujourd’hui le démarrage de la construction du parc éolien en mer de Saint-Brieuc. Les travaux s’étaleront sur 3 années. En 2021, les opérations de construction se déroulent de mai à octobre sur cinq zones situées uniquement sur la partie nord du parc.
Mar 26 2021

Saint-Brieuc offshore wind turbine towers to be fitted in Brest

Today, Ailes Marines announced that the 62 wind turbine towers for its Saint-Brieuc offshore wind farm will be assembled in the port of Brest’s new polder. This industrial plan will see the creation of new production capacity and at least 35 new jobs during the project’s construction period.
Feb 26 2021

Parc éolien en mer de Saint-Brieuc : 1500 emplois mobilisés en France

Ailes Marines annonce aujourd’hui que le projet éolien en mer de Saint-Brieuc mobilisera 1500 emplois en France, dont environ 500 en Bretagne. Ailes Marines a sélectionné pour leur savoir-faire reconnu des grands groupes internationaux, mais également des TPE-PME bretonnes spécialisées. Ainsi, le projet participe directement au développement de la filière industrielle de l’éolien en mer, en France et en Bretagne.
Jan 20 2021

Sondage IFOP – 71% des habitants des Côtes d’Armor favorables au projet de parc éolien en mer de Saint-Brieuc

Ailes Marines a fait réaliser par l’IFOP, institut de sondages et d’études de marchés, une étude sur la tendance et la perception de l’opinion publique à propos du projet de parc éolien en mer de Saint-Brieuc. Cette étude qui s’est déroulée au mois de décembre 2020, a porté sur un échantillon représentatif de la population vivant dans les départements bretons du Finistère, d’Ille-et-Vilaine, du Morbihan, des Côtes-d’Armor, ainsi qu’en Loire-Atlantique. Les résultats attestent de l’adhésion des populations costarmoricaines, bretonnes et de Loire-Atlantique au projet de parc éolien en mer de...
Dec 18 2020

Ailes Marines opte pour la méthode du forage pour installer les pieux des fondations, technique de moindre impact sur l’environnement.

Pour réduire l’impact environnemental, Ailes Marines a décidé d’utiliser la technique du forage pour installer les pieux des fondations. Cette décision a été prise après des années d’études d’ingénierie et suite à la réalisation de tests de forage à terre et en mer pour maximiser la sécurité et la protection de l’environnement. Cette décision concerne l’ensemble des emplacements des 62 fondations des éoliennes et celui de la sous-station électrique.
Dec 10 2020

Ailes Marines annonce la présentation des résultats des études environnementales et des campagnes de tests d’outillages aux acteurs du projet éolien de Saint-Brieuc.

Les impacts sonores du forage sont compatibles avec le cycle de vie normal des espèces halieutiques étudiées. Ailes Marines a décidé d’abandonner la technique de battage et de privilégier la méthode du forage pour l’installation des pieux. Les turbidités générées pendant les travaux auront une incidence faible sur le milieu. L’Ifremer valide l’état de référence des études de la ressource halieutique réalisé par Ailes Marines et RTE.
Dec 02 2020

Ailes Marines ensouillera l’intégralité des câbles inter-éoliennes du parc de Saint-Brieuc

Suite aux tests d’outillage réalisés à l’été 2020 et malgré les conditions très complexes des fonds marins du site, Ailes Marines confirme son objectif d’ensouiller à 100% l’ensemble des câbles inter-éoliennes du parc de Saint-Brieuc.​ L’ensouillage complet des câbles représenterait une avancée majeure pour la sécurité de la navigation et un pas de plus vers un maintien des activités de pêche au sein du parc.
Nov 20 2020

Ailes Marines apporte des précisions et clarifications sur le projet de parc éolien en mer de Saint-Brieuc

Ailes Marines tient à apporter des précisions et des clarifications sur de nombreuses affirmations et contre-vérités qui sont exprimées régulièrement à propos du parc éolien en mer de Saint-Brieuc. Ailes Marines rappelle que : ● La zone du parc éolien La zone de 180 km2 soumise à appel d’offres en 2011 pour l’implantation d’un parc éolien en mer au large de la Baie de Saint-Brieuc a été définie par l’Etat​, à l’issue d’un processus de concertation avec l’ensemble des acteurs du territoires mené en 2010, sous l’égide de la Conférence Régionale Mer et Littoral, à laquelle ont participé les...
Oct 02 2020

Navantia-Windar starts production of foundation elements for the Saint-Brieuc offshore wind farm at the Brest Polder

One year after the Navantia-Windar consortium was selected to manufacture the foundations of the wind turbines for the Saint-Brieuc offshore wind farm, the two companies are now established in the Brest polder and are actively collaborating with Breton companies. Seventeen local companies have already worked on the Navantia-Windar site located at the new EMR terminal in Brest. Two new contracts were signed today and the consortium is currently negotiating with 20 other companies.
Sep 16 2020

Ailes Marines has selected GE Grid Solutions to supply and install the main electrical equipment for the substation of the offshore wind farm in the Bay of Saint-Brieuc.

Ailes Marines, a company wholly owned by Iberdrola, in charge of the construction, installation and operation of the offshore wind farm in the Bay of Saint-Brieuc, today announced the selection of GE Grid Solutions, a division of GE Renewable Energy, to supply the main electrical equipment for the substation of the Saint-Brieuc offshore wind farm.
Sep 07 2020

Ailes Marines has selected the French companies Eiffage Métal and Engie Solutions for the manufacturing of the electrical substation of the offshore wind farm in the Bay of Saint-Brieuc.

Ailes Marines, a company wholly owned by Iberdrola, in charge of the construction, installation and operation of the offshore wind farm in the Bay of Saint-Brieuc, today announced the award of the contract for the construction of the wind farm's electrical substation to the two French companies Eiffage Métal and ENGIE Solutions.
June 18 2020

Iberdrola creates 1,100 jobs in France thanks to the wind farm project

Iberdrola confirms the launch of its €4 billion investment in France. The contract for the supply of the foundations, totalling €350 million, was signed this morning by the President of Iberdrola, Ignacio Galán. The components of the foundations will be assembled on Brest polder's port.
May 29 2020

Ailes Marines and Siemens Gamesa sign the contract for the supply of wind turbines for the Saint-Brieuc offshore wind farm

Ailes Marines, Iberdrola's subsidiary in charge of the development, construction, installation and operation of the offshore wind farm in the Bay of Saint-Brieuc, today announced the signature with Siemens Gamesa Renewable Energy of the contract to supply the 62 wind turbines for the Saint-Brieuc offshore wind farm.
May 27 2020

Ailes Marines selects Prysmian as supplier of submarine cables for the wind farm

Ailes Marines, in charge of the development, construction, installation and operation of the Saint-Brieuc Bay offshore wind farm, has just signed an 80 million euro contract with the Prysmian Group, a world leader in the power and telecommunication cable systems industry, to supply the inter-wind turbine cables for the Saint-Brieuc wind farm.
May 06 2020

Ailes Marines has selected Van Oord to install the foundations of the wind farm.

Ailes Marines, in charge of the construction, installation and operation of the Saint-Brieuc Bay wind farm, has selected the Dutch company Van Oord to transport and install the 62 jacket foundations (lattice steel structures) as well as the piles for the foundations of the electrical substation.
Tue 09 2020

Iberdrola acquires 100% of the capital of Ailes Marines

Iberdrola has reaffirmed its ambitions in the offshore wind energy sector, following the conclusion of an agreement to acquire 100% of the company Ailes Marines. The latter develops, builds and operates the offshore wind farm in Saint-Brieuc, France, a country that has become an increasingly strategic market for Iberdrola.
Sep 16 2019

Ailes Marines has selected Navantia to build the foundations of the wind farm.

Ailes Marines, in charge of the development, construction, installation and operation of the offshore wind farm in the Bay of Saint-Brieuc, has selected the Spanish company Navantia for the manufacture of the 62 foundations of the offshore wind turbines that will equip the wind farm.