Press release

Ailes Marines re-establishes the truth against false information about the Saint-Brieuc offshore wind farm

Lézardrieux / Saint-Brieuc / Paris – August 18, 2021 – Following numerous affirmations and untruths relayed in recent weeks by media, Ailes Marines would like to provide once again details and clarifications about the Saint-Brieuc offshore wind farm.

18

August

21

The pursuit of professional fishing activities within the park

Ailes Marines once again reminds us that the project was designed in such a way as to allow the maintenance of fishing and navigation activities within the park (orientation of wind turbine lines, spacing between wind turbines, objective of burial of cables, ...). The offshore wind farm occupies an area limited to 6% on the Large deposit (secondary deposit), or the equivalent of 1.5% of the production of scallops in the entire Bay. The Côtes d ́Armor Prefecture has put in place clear governance through a management and monitoring committee chaired by the Côtes d ́Armor prefect to monitor the progress of the work and the follow-up measures undertaken.

Presence of coral

Concerning the supposed presence of coral, Ailes Marines also recalls that a study of the initial state of the site was carried out and integrated into the impact study carried out between 2012 and 2015. On the basis of existing scientific data, in particular public scientific inventories,

the initial state of the site did not identify the presence of coral in the 75 km2 area of the Saint-Brieuc offshore wind farm.

Requesting and obtaining "protected species" exemptions

Ailes Marines recalls that in France, the destruction or disturbance of individuals of species (or their habitats) appearing on lists of protected species (established at national, regional, and departmental level) is prohibited by the French Code of the environment.

A request for a “protected species” exemption requires transparency and environmental responsibility on the part of the developer. Several conditions must be met for it to be granted, in particular the public interest, the absence of alternatives, maximum avoidance and ecological compensation up to the impact.

This initial state of the site was:

1) Carry out an impact study (in the Avoid-Reduce-Compensate philosophy),

2) Apply for a "protected species" exemption with expert advice.

These requests are examined by the DREAL, the CNPN (National Council for the Protection of Nature) issues an advisory opinion and the Minister an assent.

The “protected species” exemption responds to 3 main principles:

1) The lack of a lower impact alternative.

2) The destruction must respond to an imperative reason of overriding public interest, including of a social or economic nature.

3) The operations do not affect the conservation status of the species concerned (whether affecting individuals, breeding sites or resting areas). In return, it is requested to implement so-called compensatory measures.

The Saint-Brieuc offshore wind farm is the first offshore wind farm project in France to request and obtain exemptions.

These legally obtained “protected species” exemption requests concern 5 species of marine mammals and 54 species of birds. The file was investigated by the DREAL and the opinion of the CNPN was requested following a presentation made to the Council in 2016. An assent from the Minister of the Environment on the CNPN file was obtained on 4 July 2016.

Further information:

→ The measures put in place

The impact studies

Ailes Marines carried out the impact study of the project between 2012 and 2015, prior to the filing with the Côtes-d'Armor prefecture of the administrative authorizations required for the construction and operation of the wind farm. These studies carried out as part of the impact study were able to provide the following answers:

They do not demonstrate the consequent modification of sea currents. Jacket-type foundations also allow free circulation of water masses at the foot of the wind turbines.

They also do not demonstrate the creation of a magnetic field at the foot of wind turbines or the presence of vibrations powerful enough to alter both the marine environment and the ecosystem.

It is important to note that this impact study of the project carried out by the various design offices naturally includes an in-depth analysis of the tidal conditions as well as the strength of the currents in the bay of Saint-Brieuc (which have elsewhere thereafter is the subject of numerical modeling to study other aspects such as the diffusion of sounds or the turbidity of sea water).

The foundations of wind turbines

Ailes Marines will not proceed with the massive concreting of the bay. The foundations of wind turbines are made of steel trellises (jacket). Sealing will be well used, but in very limited quantity and only to consolidate the grip of the piles on the 3 fixing points of the jacket foundations.

Maintenance of the blades of the offshore wind farm

The blades of the Saint-Brieuc wind turbines are inspected annually by drones. They do not require cleaning operations, high winds and rain keep the tower and blades clean. Specific marine paints are also used to prevent impurities from depositing on the structure. The blades will therefore not be cleaned with fungicides deposited by helicopter. If maintenance interventions on the blades were necessary, they would be carried out by rope access technicians authorized to intervene for this type of intervention

The production of the offshore wind farm

In the case of the Saint-Brieuc Bay offshore wind farm, the load factor is estimated at 40% at full power. However, with the wind turbines turning as soon as the wind reaches 12 km / h, the park will therefore produce energy 90% of the time.
Further information:
→ Wind farm production

The dismantling

The dismantling of the wind farm will be carried out at the end of the operating period, as well as a restoration of the site. This is a regulatory requirement. As specified in the Convention on the Use of the Public Maritime Domain signed with the State. A financial guarantee will be deposited by Ailes Marines when the wind farm is commissioned, to prevent any breach of this obligation

The carbon footprint of the project

Compared to the French electricity mix, the carbon return time for the Saint-Brieuc offshore wind farm is 4 years and 5 months. The carbon payback time is the time necessary for an installation, by substituting the electricity produced, to avoid the GHG emissions that were necessary for its manufacture, installation, maintenance, and dismantling.
Further information:
→ CPDP carbon footprint

Saint-Brieuc and Landivisiau, two totally separate projects

The offshore wind farm in the Bay of Saint-Brieuc and the construction of the combined cycle gas plant at Landivisiau are completely unrelated.. Electricity Transmission Network (RTE) continuously and very precisely forecasts electricity needs and adapts its means of production accordingly. In mainland France, the very good interconnection of the networks makes it possible to distribute the electricity produced on a national scale according to needs.
logo-ailes-marines-baseline-blue

About Ailes Marines

Winner of a national call for projects with the Baie de Saint-Brieuc offshore wind farm project, AILES MARINES is in charge of the development, construction, installation and operation of the offshore wind farm. It is a simplified joint stock company (SAS), 100% owned by IBERDROLA.
Key figures for the Baie de Saint-Brieuc offshore wind project:

  • 75 km2 in area
  • 62 Siemens Gamesa SG 8.0-167 DD 8 MW wind turbines
  • 496 MW of installed capacity
  • 1,820 GWh/year of production, i.e. the annual electricity consumption of 835,000 inhabitants (including heating)
symorg-logo-contact

Press Relations & Communication

Jean Christophe Labastugue
Manager

All Press Releases

Fin de la première phase des travaux en mer du parc éolien de Saint-Brieuc

Ailes Marines announces today the end of the first phase of the construction works for the year 2021. The operations are fully completed and the AEOLUS vessel is ready to leave the area. It will...

The 2021 inter-array cable pre-trenching campaign is now completed

Ailes Marines announces the end of the pre-trenching campaign for the inter-wind turbine cable routes. The vessel Aethra left the work area on 14 August, almost 5 weeks ahead of schedule.

AEOLUS vessel resumption to drilling work

Ailes Marines announces, with the agreement of the Préfecture Maritime, the resumption of drilling works by the vessel AEOLUS today. The absence of pollution has been confirmed by the air and sea...

Processing a drilling rig incident on the AEOLUS vessel

An incident was reported this morning by the captain of the ship AEOLUS to the CROSS Corsen (Regional Operational Center for Surveillance and Rescue) and the maritime coordination...

Resumption of drilling work on the Saint-Brieuc offshore wind farm

Ailes Marines announces the return of the AEOLUS to the area from July 16, 2021, following the agreement of the maritime authorities. The jack-up vessel of the Van Oord company is responsible for drilling and installing the foundation piles for the offshore wind farm. After a complete review of the vessel's tools and equipment carried out by Van Oord in the Netherlands, all of the work control and monitoring protocols have been reassessed. Ailes Marines also announces the signing of an agreement with CEDRE.

Ailes Marines provides details on the incident of 14 June 2021

The jack up vessel AEOLUS operated by the company Van Oord, in charge of drilling and installing the foundation piles for the offshore wind farm, left the Bay of Saint-Brieuc today for...

Immobilisation of the vessel AEOLUS for tooling verification

The jack up vessel AEOLUS in charge of drilling and installing the piles for the foundations of the Saint-Brieuc offshore wind farm is currently immobilised on site. This...

Renforcement des suivis environnementaux pendant les travaux de forage

Durant la première phase des travaux de forage qui se déroule de mai à octobre 2021 sur la zone nord du périmètre du parc de Saint-Brieuc, Ailes Marines instaure des mesures renforcées de suivis en...

Démarrage de la construction du parc éolien en mer de Saint-Brieuc

Ailes Marine confirme aujourd’hui le démarrage de la construction du parc éolien en mer de Saint-Brieuc. Les travaux s’étaleront sur 3 années. En 2021, les opérations de construction se déroulent de...

Saint-Brieuc offshore wind turbine towers to be fitted in Brest

Today, Ailes Marines announced that the 62 wind turbine towers for its Saint-Brieuc offshore wind farm will be assembled in the port of Brest’s new polder. This industrial plan will see the creation of new production capacity and at least 35 new jobs during the project’s construction period.

Parc éolien en mer de Saint-Brieuc : 1500 emplois mobilisés en France

Ailes Marines annonce aujourd’hui que le projet éolien en mer de Saint-Brieuc mobilisera 1500 emplois en France, dont environ 500 en Bretagne. Ailes Marines a sélectionné pour leur savoir-faire...

Sondage IFOP – 71% des habitants des Côtes d’Armor favorables au projet de parc éolien en mer de Saint-Brieuc

Ailes Marines a fait réaliser par l’IFOP, institut de sondages et d’études de marchés, une étude sur la tendance et la perception de l’opinion publique à propos du projet de parc éolien en mer de...

Ailes Marines opte pour la méthode du forage pour installer les pieux des fondations, technique de moindre impact sur l’environnement.

To reduce the environmental impact, Ailes Marines decided to use the drilling technique to install the foundation piles. This decision was made after years of study...

Ailes Marines annonce la présentation des résultats des études environnementales et des campagnes de tests d’outillages aux acteurs du projet éolien de Saint-Brieuc.

Les impacts sonores du forage sont compatibles avec le cycle de vie normal des espèces halieutiques étudiées. Ailes Marines a décidé d’abandonner la technique de battage et de privilégier la méthode...

Ailes Marines ensouillera l’intégralité des câbles inter-éoliennes du parc de Saint-Brieuc

Suite aux tests d’outillage réalisés à l’été 2020 et malgré les conditions très complexes des fonds marins du site, Ailes Marines confirme son objectif d’ensouiller à 100% l’ensemble des câbles...

Ailes Marines apporte des précisions et clarifications sur le projet de parc éolien en mer de Saint-Brieuc

Ailes Marines tient à apporter des précisions et des clarifications sur de nombreuses affirmations et contre-vérités qui sont exprimées régulièrement à propos du parc éolien en mer de Saint-Brieuc....

Navantia-Windar starts production of foundation elements for the Saint-Brieuc offshore wind farm at the Brest Polder

One year after the Navantia-Windar consortium was selected to manufacture the foundations of the wind turbines for the Saint-Brieuc offshore wind farm, the two companies are now established in the Brest polder...

Ailes Marines has selected GE Grid Solutions to supply and install the main electrical equipment for the substation of the offshore wind farm in the Bay of Saint-Brieuc.

Ailes Marines, a company wholly owned by Iberdrola, in charge of the construction, installation and operation of the offshore wind farm in the Bay of Saint-Brieuc, announced today the acquisition of the...

Ailes Marines has selected the French companies Eiffage Métal and Engie Solutions for the manufacturing of the electrical substation of the offshore wind farm in the Bay of Saint-Brieuc.

Ailes Marines, a company wholly owned by Iberdrola, in charge of the construction, installation and operation of the offshore wind farm in the Bay of Saint-Brieuc, announced today that...

Ailes Marines has selected Saipem for the transport and installation of the "jacket" type foundations for the Saint-Brieuc offshore wind farm substation.

Ailes Marines, a company of the Iberdrola Group in charge of the development, construction, installation and operation of the offshore wind farm in the Bay of Saint-Brieuc, has...

Iberdrola creates 1,100 jobs in France thanks to the wind farm project

Iberdrola confirms the launch of its €4 billion investment in France. The contract for the supply of the foundations, which totals 350 million euros, will be awarded to Iberdrola....

Ailes Marines and Siemens Gamesa sign the contract for the supply of wind turbines for the Saint-Brieuc offshore wind farm

Ailes Marines, Iberdrola's subsidiary in charge of the development, construction, installation and operation of the offshore wind farm in the Bay of Saint-Brieuc, has announced...

Ailes Marines selects Prysmian as supplier of submarine cables for the wind farm

Ailes Marines, in charge of the development, construction, installation and operation of the offshore wind farm in the Bay of Saint-Brieuc, has just signed an agreement with the Group....

Ailes Marines has selected Van Oord to install the foundations of the wind farm.

Ailes Marines, in charge of the construction, installation and operation of the Saint-Brieuc Bay wind farm, has selected the Dutch company Van Oord to transport and operate the wind farm....

Iberdrola acquires 100% of the capital of Ailes Marines

Iberdrola has reaffirmed its ambitions in the offshore wind energy sector, following the conclusion of an agreement to acquire 100% of the company Ailes Marines. This company develops, builds and operates...

Ailes Marines has selected Navantia to build the foundations of the wind farm.

Ailes Marines, in charge of the development, construction, installation and operation of the offshore wind farm in the Bay of Saint-Brieuc, has selected the Spanish company Ailes Marines, which is in charge of the development, construction, installation and operation of the offshore wind farm in the Bay of...