Press release

End of the first phase of work at sea on the Saint-Brieuc wind farm

Lézardrieux / Saint-Brieuc / Paris – November 1, 2021 –

Ailes Marines today announces the end of the first phase of construction work for the year 2021. The operations are completely completed, the AEOLUS ship is ready to leave the area. He is waiting for a favorable weather window for his return to floating, in order to reach his home port. Offshore construction work on the park will resume on March 1, 2022 at the latest.

01
November
21

End of the first phase of construction work for the year 2021

The first phase of work at sea for the year 2021 began on May 3 and ended on October 31. This schedule was announced to the local Nautical Commission last March and corresponds to a technical shutdown of nautical resources and tools.

Three positions drilled and equipped with piles

In consultation with the CDPMEM22 in the presence of State services, Ailes Marines agreed to concentrate the first phase of work in 2021 only on the northern zone of the park, in order to allow the continuation of fishing activities in the southern part. This northern area is characterized by the presence of extremely hard rocks such as sandstone. However, the tools have demonstrated their efficiency by their gradual increase in power, including on the hardest rocks.

To date, the AEOLUS vessel has carried out drilling on 5 wind turbine locations and on the location of the electrical substation. A total of 19 drillings were carried out by the ship, three-quarters of which were at the desired depth objective. The piles were installed in three positions, those of the SB30 and SB26 wind turbines and that of the electrical substation.

Pre-slicing operations completed since August

Five weeks ahead of the schedule announced by Ailes Marines , the pre-trenching operations for burying the cables and moving the rock blocks were completed in August 2021. The Aethra ship also carried out preparatory operations concerning the 2022 work sequence, also located in the northern part.
As a reminder and in order to allow fishing activities to continue when the park is in operation, Ailes Marines has set itself the objective of burying all of the inter-wind turbine cables (90 km of cables) in the park, despite the numerous technical constraints.

Additional turbidity and noise control measures

In consultation with the CDPMEM22 and to respond to their request, Ailes Marines carried out, during this first installation phase, reinforced turbidity and noise control measures. These measures are in addition to the forty environmental measures included in the prefectural authorizations for the project and carried out by Ailes Marines .

During the drilling of the anchor piles for the wind turbine foundations, Ailes Marines carried out real-time monitoring and monitoring of turbidity and noise. Noise measurements were carried out near the drilling point continuously by a RUBHY acoustic buoy equipped with hydrophones, developed by two Breton companies RTSYS (electronics) and GISMAN (mooring).

For the definition of the protocols and the scientific analysis of the data, Ailes Marines contracted, on the recommendations of the CDPMEM22, the Société d'Observation Multi-Modale de l'Environnement (SOMME), a specialized Breton design office (29). in the observation of marine ecosystems. Drilling noise is between 177 dB and 191 dB at the source. These emissions fall between 137 and 151 dB just 100 m from the drilling point. These sound levels correspond to common underwater noise conditions with no impact on marine animals. These noises are equivalent to an ambient noise level representative of an area frequented by several types of vessels (fishing vessels, tugboats).

Compensation measures for professional fishermen

During this first phase of work, Ailes Marines set up an online information space .

On this site, professional fishermen whose activity could be impacted during the park construction work phase (2021-2023) were able to reference themselves and thus benefit from precise information on the amount of compensation they received. could benefit.

 

All sea users as well as the general public can follow the progress of the work live on the website.

Resumption of construction work in March 2022

Offshore construction work will resume on March 1, 2022 at the latest. The resumption of work will be governed by a prefectural decree. In 2022, Ailes Marines will install the piles, cables, and install the jacket foundations and the electrical substation.
The construction work at sea will last until 2023. All industrial means will be implemented so that the wind farm is fully operational at the end of 2023.

logo-marine-wings-baseline-blue

About Ailes Marines

Winner of a national call for projects with the Saint-Brieuc Bay offshore wind farm project, AILES MARINES is in charge of the development, construction, installation and operation of the offshore wind farm. It is a simplified joint stock company (SAS), 100% owned by IBERDROLA. The key figures of the Saint-Brieuc Bay offshore wind project:

  • 75 km2 of area
  • 62 Siemens Gamesa SG 8.0-167 DD 8 MW wind turbines
  • 496 MW of installed power
  • 1,820 GWh/year of production, i.e. the annual electricity consumption of 835,000 inhabitants (heating included)

All Press releases

Jul 02 2024

The Saint-Brieuc offshore wind farm is once again accessible to maritime and fishing activities

The resumption of maritime and fishing activities in the Saint-Brieuc offshore wind farm has been effective since July 1, 2024.

May 28 2024

Iberdrola commissions the second French offshore wind farm and the first in Brittany

Iberdrola, through its subsidiary Ailes Marines , today announces the full commissioning of the second French offshore wind farm and the first in Brittany. At this...
Apr 25 2024

IBReizh program: Ailes Marines subsidiary of Iberdrola announces 3 selected innovative projects

In October 2023, as part of the IBReizh program, Ailes Marines , a subsidiary of Iberdrola, launched in partnership with the Pôle Mer Bretagne Atlantique a Call for...
Dec 18 2023

All of the wind turbines at the Saint-Brieuc offshore wind farm are installed

The installation phase of the wind turbines in the Saint-Brieuc park is complete. The Brave Tern jack-up vessel from the Norwegian company Fred Olsen...
Jul 06 2023

The second French offshore wind farm produces its first green megawatt hours in Brittany

Ailes Marines , a company 100% owned by the Iberdrola group, today announces the production of the first megawatt hours from the Saint-Brieuc offshore wind farm....
May 12 2023

Ailes Marines , a subsidiary of Iberdrola, has installed Brittany's first offshore wind turbine.

The installation of the first of the 62 wind turbines which will equip the Saint-Brieuc wind farm was carried out on May 9 by the contractor of Ailes Marines , the company Siemens...
Mar 27 2023

Resumption of drilling and installation work on the wind farm in Saint-Brieuc Bay.

Ailes Marines announces today the resumption of drilling and installation work on the wind farm in the bay of Saint-Brieuc. These operations will mobilize for...
Mar 03 2023

Pioneering environmental studies, recognized by the international scientific community

PLos One and Limnology & Oceanography Methods, two international scientific publications, have validated the protocols for measuring the effects of noise on...
Mar 02 2023

Ailes Marines , a subsidiary of Iberdrola, inaugurates the temporary technical base of the Saint-Brieuc offshore wind farm on the port of Saint-Malo

The temporary technical base of the Saint-Brieuc offshore wind farm was inaugurated on Friday February 24, 2023 by Daniel Cueff, Vice-President of the Region...
Dec 20 2022

Signature of a partnership to study the feasibility of a sustainable and integrated aquaculture farm within the Saint-Brieuc offshore wind farm.

Ailes Marines , a company 100% owned by the Iberdrola group, and the Northern Brittany Regional Shellfish Farming Committee (CRCBN) today signed a...