Press release

Ailes Marines announces the presentation of the results of environmental studies and tooling test campaigns to stakeholders in the Saint-Brieuc wind project.

The noise impacts of drilling are compatible with the normal life cycle of the fish species studied. Ailes Marines decided to abandon the driving technique and favor the drilling method for the installation of the piles. Turbidity generated during the work will have a low impact on the environment. Ifremer validates the reference state of the fishery resource studies carried out by Ailes Marines and RTE.

Saint-Brieuc / Paris – December 10, 2020 – After 2 years of studies and monitoring, Ailes Marines and the scientists involved presented on December 10 to the Management and Monitoring Committee chaired by the Prefect of Côtes d'Armor and bringing together the main actors of the project:

❖ The results of additional studies requested by the CDPMEM22 on the impact of noise and turbidity in the perimeter of the Saint-Brieuc offshore wind farm.
❖ The results of this summer's tooling test campaigns.
❖ The Ifremer report on the quality of the reference state of the
fishery resource studies carried out by Ailes Marines and RTE.

● Studies on the impact of noise: new knowledge for MRE

In addition to the 135 measurements included in the prefectural authorizations for the project (of which more than 40 concern environmental aspects), Ailes Marines has launched an unprecedented campaign of in situ of noise emitted during tool tests in order to more precisely characterize the impact of the works on the marine environment.

These measurements complemented the laboratory studies carried out on the fish species of interest, validated by the CDPMEM22, relating to scallops , clams, lobsters and cuttlefish.

These scientific studies were conducted by Dr. Laurent Chauvaud, research director at the CNRS, Prof. Frédéric Olivier from the National Museum of Natural History and Dr. Delphine Mathias.

The studies on the impact of noise on cuttlefish were carried out by Michel André, Professor at the Polytechnic University of Catalonia (UPC) and Director of the Bioacoustic Applications Laboratory (LAB).

This study campaign, which took place over 24 months, represents a world first for research in marine biology. This is in fact the first time that studies of this scale on the impact of noise on fisheries resources have been carried out as part of the construction of an offshore wind farm.

The methodology implemented by the various researchers made it possible to provide new scientific knowledge concerning the impacts of noise on the species studied.

The results of these studies carried out in the laboratory and on site demonstrate that:

❖ The significant effects of the tools used are compatible with the normal life cycle of the species studied (scallops, clams, cuttlefish)
❖ The noises tested do not have a major impact on the organisms studied (scallops, clams , sea almond).
❖ The radius of incidence for drilling noise on the seiche is a few tens of meters around the work zone.

These excellent studies and their unique and original results will be submitted to international scientific publications.

In situ measurements show that the work will generate sounds of a sound intensity comparable to, among others, speedboats, cruise ships, container ships, jet skis.

Alongside these studies, Ailes Marines also carried out turbidity readings generated by testing of trenching and drilling tools in order to more precisely characterize the impact of the work on the environment.

The results of these studies demonstrate that the turbidity generated during the work will have a low impact on the environment.

❖ For drilling, the turbidities measured are less than 5 NTU whatever the distance (between 400 and 800 m from the drilling point).
❖ For slicing, average turbidities are always less than 6 NTU (400m from the slicing point). Although some occasional peaks at 17 NTU are observed.

The NTU (Nephelometric Tu rbidity Unit) is the standard unit of measurement for turbidity. If the NTU is less than 5 the water is clear, between 5 and 30 slightly cloudy, and above 50 the water is cloudy.

● Tooling tests

During the month of September 2020, Ailes Marines carried out offshore drilling on the site of the Saint-Brieuc bay wind farm.

Following the results of these tests, Ailes Marines decided to abandon the driving technique and use the drilling method – significantly less noisy for the environment – ​​for the installation of the piles, for all locations. foundations. The impacts on fish species and marine mammals will therefore be very significantly reduced.

● Ifremer's expertise on defining the reference state of the fishery resource

The authorizations issued by the Côtes d'Armor prefecture in April 2017 for the construction and operation of the wind farm provided for the creation of a reference state of the fishery resource, before the start of installation work at sea.

Following questions from the fisheries committees, the prefect of Côtes d'Armor requested the opinion of Ifremer in July 2020 on the protocols proposed by Ailes Marines and RTE, for the achievement of this reference state.

In its report submitted to the prefect of Côtes d'Armor, Ifremer considers that:

“The protocols for carrying out the reference state and monitoring (in the works and operation phase) of the fish populations proposed by Ailes Marines and RTE as part of the Saint-Brieuc Bay offshore wind project and its electrical connection , and based on the collection of data through “experimental tides ”, are sufficiently robust to make it possible to detect a possible impact of the park and its connection on the targeted fish species .

10

December

20
logo-marine-wings-baseline-blue

About Ailes Marines

Winner in April 2012 of a national call for projects with the Saint-Brieuc Bay offshore wind farm project, AILES MARINES is in charge of the development, construction, installation and operation of the park. offshore wind farm. It is a simplified joint stock company (SAS), 100% owned by IBERDROLA.
The key figures of the Saint-Brieuc Bay offshore wind project:

  • 75 km2 of area
  • 62 Siemens-Gamesa 8 MW wind turbines
  • 496 MW of installed power
  • 1,820 GWh/year of production, i.e. the annual electricity consumption of 835,000 inhabitants (heating included)

All Press releases

Jul 02 2024

The Saint-Brieuc offshore wind farm is once again accessible to maritime and fishing activities

The resumption of maritime and fishing activities in the Saint-Brieuc offshore wind farm has been effective since July 1, 2024.

May 28 2024

Iberdrola commissions the second French offshore wind farm and the first in Brittany

Iberdrola, through its subsidiary Ailes Marines , today announces the full commissioning of the second French offshore wind farm and the first in Brittany. At this...
Apr 25 2024

IBReizh program: Ailes Marines subsidiary of Iberdrola announces 3 selected innovative projects

In October 2023, as part of the IBReizh program, Ailes Marines , a subsidiary of Iberdrola, launched in partnership with the Pôle Mer Bretagne Atlantique a Call for...
Dec 18 2023

All of the wind turbines at the Saint-Brieuc offshore wind farm are installed

The installation phase of the wind turbines in the Saint-Brieuc park is complete. The Brave Tern jack-up vessel from the Norwegian company Fred Olsen...
Jul 06 2023

The second French offshore wind farm produces its first green megawatt hours in Brittany

Ailes Marines , a company 100% owned by the Iberdrola group, today announces the production of the first megawatt hours from the Saint-Brieuc offshore wind farm....
May 12 2023

Ailes Marines , a subsidiary of Iberdrola, has installed Brittany's first offshore wind turbine.

The installation of the first of the 62 wind turbines which will equip the Saint-Brieuc wind farm was carried out on May 9 by the contractor of Ailes Marines , the company Siemens...
Mar 27 2023

Resumption of drilling and installation work on the wind farm in Saint-Brieuc Bay.

Ailes Marines announces today the resumption of drilling and installation work on the wind farm in the bay of Saint-Brieuc. These operations will mobilize for...
Mar 03 2023

Pioneering environmental studies, recognized by the international scientific community

PLos One and Limnology & Oceanography Methods, two international scientific publications, have validated the protocols for measuring the effects of noise on...
Mar 02 2023

Ailes Marines , a subsidiary of Iberdrola, inaugurates the temporary technical base of the Saint-Brieuc offshore wind farm on the port of Saint-Malo

The temporary technical base of the Saint-Brieuc offshore wind farm was inaugurated on Friday February 24, 2023 by Daniel Cueff, Vice-President of the Region...
Dec 20 2022

Signature of a partnership to study the feasibility of a sustainable and integrated aquaculture farm within the Saint-Brieuc offshore wind farm.

Ailes Marines , a company 100% owned by the Iberdrola group, and the Northern Brittany Regional Shellfish Farming Committee (CRCBN) today signed a...