Select a page

Press release

Ailes Marines has selected Van Oord for the transport and installation of the foundations of the Saint-Brieuc offshore wind farm.
 

Saint-Brieuc / Paris / Rotterdam - May 6, 2020 - Ailes Marines, in charge of the construction, installation and operation of the Saint-Brieuc Bay wind farm, has selected the Dutch company Van Oord to transport and install the 62 jacket foundations (metal lattice structures) as well as the piles for the foundations of the electrical substation.

6

May

20

Transport and installation work

Van Oord will begin offshore operations in 2021 with the installation of the anchoring piles, using its vessel Aeolus. The Aeolus will be assisted by a second ship in 2022, for the installation of the jacket foundations, which will be manufactured in Fene (Spain) and Brest (France).

Built specifically for the installation of offshore wind farms, the Aeolus was commissioned in 2014. Its main crane has a lifting capacity of more than 1,600 tonnes. The Aeolus is fully suitable for the transport and installation of foundations and wind turbines. Its advanced lifting system, with its giant legs, each measuring 85 metres and weighing 1,280 tonnes, allows the Aeolus to be raised and operate in water depths of up to 45 metres.

A partnership based on trust

Prysmian will provide a complete turnkey package including the design, supply, installation and all testing for the commissioning of the 90 km of 66 kV three-core subsea High Voltage AC (HVAC) high voltage three-core cable with XLPE insulation. The phases of the cables (cores and insulation) will be manufactured in the Prysmian Group's plants located in Montereau-Fault-Yonne and Gron (France), and the final assembly of the three-core cables will be carried out in Nordenham (Germany). Delivery and commissioning are scheduled for the end of 2022.

Saint-Brieuc offshore wind farm

The Saint-Brieuc offshore wind farm will be located in the Bay of Saint-Brieuc in Brittany, 16.3 kilometres off the French coast. When completed, the wind farm, with a total capacity of 496 MW, will produce 1,820 GWh per year, equivalent to the annual electricity consumption of 835,000 inhabitants. Installation work will take several months and will continue until 2022. The wind farm will be fully operational in 2023.

"Van Oord has been carrying out various projects in France for a long time. The most recent example is our participation in the various phases of deepening the Seine. The Saint-Brieuc project will be our first offshore wind farm project in France and I am proud that we are participating in it. Especially as we are delighted to have the opportunity to work with Iberdrola again. By carrying out this offshore wind farm project, we are also contributing to the European objective of reaching 32% renewable energy by 2030. »

Pieter van Oord

CEO, Van Oord

"After making the investment decision, Ailes Marines is pleased to sign this contract with Van Oord to transport and install the 62 jacket foundations and piles for the electrical substation foundation of the Saint-Brieuc project. This project will play an important role in France's transition to a green economy. Given the difficult conditions linked to the pandemic crisis, we are also contributing to the recovery of industrial activity in France and the rest of Europe. »

Javier Garcia Perez

President of Ailes Marines, International Offshore Director of Iberdrola

aeolus

The Aeolus in brief

Lifting capacity

1000 tonnes

Height of the feet

50 meters

Weight of one foot

1200 tonnes

Depth of operation

30 meters

In December 2019, Van Oord signed a contract for preliminary, design and engineering work. As a result, construction of the subsea tool to carry out these operations has already begun. It will be delivered by the end of the year.

logo-ailes-marines-baseline-blue

About Ailes Marines

Winner of a national tender with the Baie de Saint-Brieuc offshore wind farm project, AILES MARINES is in charge of the development, construction, installation and operation of the offshore wind farm. It is a simplified joint stock company (SAS), 100% owned by IBERDROLA Key figures for the Baie de Saint-Brieuc offshore wind project: - 75 km2 area - 62 Siemens Gamesa SG 8.0-167 DD wind turbines, of 8 MW unit capacity - 496 MW installed capacity - 1,820 GWh/year output, equivalent to the annual electricity consumption of 835,000 inhabitants (including heating) All information concerning the Saint-Brieuc offshore wind farm project developed by the company Ailes Marines is available on the website https://ailes-marines.bzh/ You can follow Ailes Marines news on twitter @AilesMarines

  • 75 km2 in area
  • 62 8 MW Siemens-Gamesa wind turbines
  • 496 MW of installed capacity
  • 1,820 GWh/year of production, i.e. the annual electricity consumption of 835,000 inhabitants (including heating)
Van Oord

About Van Oord

Van Oord is a Dutch family business with 150 years of experience as an international shipping contractor. It specialises in dredging, onshore infrastructure in the Netherlands as well as oil and gas infrastructure and offshore wind energy. Its parent company is located in Rotterdam. Van Oord has 5,000 employees, who in 2019 were working on 200 projects in 44 countries. Its fleet consists of 70 vessels and a significant amount of specific ancillary equipment. Maritime expertise is Van Oord's trademark. By implementing innovative, ingenious and sustainable solutions, the company wants to contribute to creating a better world for future generations.

 

For more information:
Please contact Robert de Bruin, Head of Communications and Markets, T +31 (0)88 8268234, M +31 (0)6 53440890, E robert.debruin@vanoord.com.

symorg-logo-contact

Press Relations & Communication

Jean Christophe Labastugue
Manager

All Press Releases

Fin de la première phase des travaux en mer du parc éolien de Saint-Brieuc

Ailes Marines announces today the end of the first phase of the construction works for the year 2021. The operations are fully completed and the AEOLUS vessel is ready to leave the area. It will...

Ailes Marines re-establishes the truth against false information about the Saint-Brieuc offshore wind farm

Following numerous assertions and untruths relayed in recent weeks by various media, Ailes Marines would like to once again provide details and clarifications to...

The 2021 inter-array cable pre-trenching campaign is now completed

Ailes Marines announces the end of the pre-trenching campaign for the inter-wind turbine cable routes. The vessel Aethra left the work area on 14 August, almost 5 weeks ahead of schedule.

AEOLUS vessel resumption to drilling work

Ailes Marines announces, with the agreement of the Préfecture Maritime, the resumption of drilling works by the vessel AEOLUS today. The absence of pollution has been confirmed by the air and sea...

Processing a drilling rig incident on the AEOLUS vessel

An incident was reported this morning by the captain of the ship AEOLUS to the CROSS Corsen (Regional Operational Center for Surveillance and Rescue) and the maritime coordination...

Resumption of drilling work on the Saint-Brieuc offshore wind farm

Ailes Marines announces the return of the AEOLUS to the area from July 16, 2021, following the agreement of the maritime authorities. The jack-up vessel of the Van Oord company is responsible for drilling and installing the foundation piles for the offshore wind farm. After a complete review of the vessel's tools and equipment carried out by Van Oord in the Netherlands, all of the work control and monitoring protocols have been reassessed. Ailes Marines also announces the signing of an agreement with CEDRE.

Ailes Marines provides details on the incident of 14 June 2021

The jack up vessel AEOLUS operated by the company Van Oord, in charge of drilling and installing the foundation piles for the offshore wind farm, left the Bay of Saint-Brieuc today for...

Immobilisation of the vessel AEOLUS for tooling verification

The jack up vessel AEOLUS in charge of drilling and installing the piles for the foundations of the Saint-Brieuc offshore wind farm is currently immobilised on site. This...

Renforcement des suivis environnementaux pendant les travaux de forage

Durant la première phase des travaux de forage qui se déroule de mai à octobre 2021 sur la zone nord du périmètre du parc de Saint-Brieuc, Ailes Marines instaure des mesures renforcées de suivis en...

Démarrage de la construction du parc éolien en mer de Saint-Brieuc

Ailes Marine confirme aujourd’hui le démarrage de la construction du parc éolien en mer de Saint-Brieuc. Les travaux s’étaleront sur 3 années. En 2021, les opérations de construction se déroulent de...

Saint-Brieuc offshore wind turbine towers to be fitted in Brest

Today, Ailes Marines announced that the 62 wind turbine towers for its Saint-Brieuc offshore wind farm will be assembled in the port of Brest’s new polder. This industrial plan will see the creation of new production capacity and at least 35 new jobs during the project’s construction period.

Parc éolien en mer de Saint-Brieuc : 1500 emplois mobilisés en France

Ailes Marines annonce aujourd’hui que le projet éolien en mer de Saint-Brieuc mobilisera 1500 emplois en France, dont environ 500 en Bretagne. Ailes Marines a sélectionné pour leur savoir-faire...

Sondage IFOP – 71% des habitants des Côtes d’Armor favorables au projet de parc éolien en mer de Saint-Brieuc

Ailes Marines a fait réaliser par l’IFOP, institut de sondages et d’études de marchés, une étude sur la tendance et la perception de l’opinion publique à propos du projet de parc éolien en mer de...

Ailes Marines opte pour la méthode du forage pour installer les pieux des fondations, technique de moindre impact sur l’environnement.

To reduce the environmental impact, Ailes Marines decided to use the drilling technique to install the foundation piles. This decision was made after years of study...

Ailes Marines annonce la présentation des résultats des études environnementales et des campagnes de tests d’outillages aux acteurs du projet éolien de Saint-Brieuc.

Les impacts sonores du forage sont compatibles avec le cycle de vie normal des espèces halieutiques étudiées. Ailes Marines a décidé d’abandonner la technique de battage et de privilégier la méthode...

Ailes Marines ensouillera l’intégralité des câbles inter-éoliennes du parc de Saint-Brieuc

Suite aux tests d’outillage réalisés à l’été 2020 et malgré les conditions très complexes des fonds marins du site, Ailes Marines confirme son objectif d’ensouiller à 100% l’ensemble des câbles...

Ailes Marines apporte des précisions et clarifications sur le projet de parc éolien en mer de Saint-Brieuc

Ailes Marines tient à apporter des précisions et des clarifications sur de nombreuses affirmations et contre-vérités qui sont exprimées régulièrement à propos du parc éolien en mer de Saint-Brieuc....

Navantia-Windar starts production of foundation elements for the Saint-Brieuc offshore wind farm at the Brest Polder

One year after the Navantia-Windar consortium was selected to manufacture the foundations of the wind turbines for the Saint-Brieuc offshore wind farm, the two companies are now established in the Brest polder...

Ailes Marines has selected GE Grid Solutions to supply and install the main electrical equipment for the substation of the offshore wind farm in the Bay of Saint-Brieuc.

Ailes Marines, a company wholly owned by Iberdrola, in charge of the construction, installation and operation of the offshore wind farm in the Bay of Saint-Brieuc, announced today the acquisition of the...

Ailes Marines has selected the French companies Eiffage Métal and Engie Solutions for the manufacturing of the electrical substation of the offshore wind farm in the Bay of Saint-Brieuc.

Ailes Marines, a company wholly owned by Iberdrola, in charge of the construction, installation and operation of the offshore wind farm in the Bay of Saint-Brieuc, announced today that...

Ailes Marines has selected Saipem for the transport and installation of the "jacket" type foundations for the Saint-Brieuc offshore wind farm substation.

Ailes Marines, a company of the Iberdrola Group in charge of the development, construction, installation and operation of the offshore wind farm in the Bay of Saint-Brieuc, has...

Iberdrola creates 1,100 jobs in France thanks to the wind farm project

Iberdrola confirms the launch of its €4 billion investment in France. The contract for the supply of the foundations, which totals 350 million euros, will be awarded to Iberdrola....

Ailes Marines and Siemens Gamesa sign the contract for the supply of wind turbines for the Saint-Brieuc offshore wind farm

Ailes Marines, Iberdrola's subsidiary in charge of the development, construction, installation and operation of the offshore wind farm in the Bay of Saint-Brieuc, has announced...

Ailes Marines selects Prysmian as supplier of submarine cables for the wind farm

Ailes Marines, in charge of the development, construction, installation and operation of the offshore wind farm in the Bay of Saint-Brieuc, has just signed an agreement with the Group....

Iberdrola acquires 100% of the capital of Ailes Marines

Iberdrola has reaffirmed its ambitions in the offshore wind energy sector, following the conclusion of an agreement to acquire 100% of the company Ailes Marines. This company develops, builds and operates...

Ailes Marines has selected Navantia to build the foundations of the wind farm.

Ailes Marines, in charge of the development, construction, installation and operation of the offshore wind farm in the Bay of Saint-Brieuc, has selected the Spanish company Ailes Marines, which is in charge of the development, construction, installation and operation of the offshore wind farm in the Bay of...