The Aeolus vessel has completed its drilling and pile installation operations for the 2022 campaign

28

November

22
As of November 28, the Aeolus ship has finalized the 40th wind turbine position.

Three days ago, it returned to its home port in Vlissingen (Netherlands) to carry out its in-depth annual maintenance (cleaning and checking of tools, machines and drills) which will last between 1 and 3 months, depending on the needs identified. .

The Aeolus will return to the work area during the first quarter of 2023 , to continue drilling and pile installation operations on the 22 remaining wind turbine positions out of a total of 62.

At the same time, the campaign for laying inter-wind cables, supplied and installed by the Prysmian company, will begin during the month of December depending on weather conditions.