The Aeolus vessel has completed its drilling and pile installation operations for the 2022 campaign

The Aeolus vessel has completed its drilling and pile installation operations for the 2022 campaign

As of November 28, 2022, the Aeolus ship has finalized the 40th wind turbine position. Three days ago, it returned to its home port in Vlissingen (Netherlands) to carry out its in-depth annual maintenance (cleaning and checking of tools, machines and drills) which will last between 1 and 3 months depending on the needs identified. The Aeolus will return to the work area during the first quarter of 2023, to continue drilling and pile installation operations on the 22 remaining wind turbine positions out of a total of 62.

Launch of the IBReizh program

Launch of the IBReizh program

In parallel with the deployment of the offshore wind farm in the bay of Saint-Brieuc, the Brittany Region, represented by its president Loïg Chesnais-Girard, and Ailes Marines , today signed the IBReizh program agreement, intended to support projects on Breton territory.

Electrical substation evacuation drill

Electrical substation evacuation drill

On November 28, 2022, Ailes Marines organized its first evacuation exercise on board the electrical substation, at the heart of the Saint-Brieuc Bay offshore wind farm. The aim of this training was to evacuate 2 injured people, one by helicopter and the other by transfer boat, with the aim of verifying knowledge and internal Health and Safety (H&S) processes.

Inauguration of the Haizea Breizh workshop in Brest

Inauguration of the Haizea Breizh workshop in Brest

The offshore wind project in the bay of Saint-Brieuc, developed by Ailes Marines , contributed to the installation of the second industrial plant on the Brest polder during the installation of Haizea Breizh on the port in 2021. Operational since the end of summer 2022, the workshop was inaugurated this Thursday, October 6.

The company Ailes Marines presents at the Breton Economic Forum

The company Ailes Marines presents at the Breton Economic Forum

The Ailes Marines company had the pleasure of participating in the Breton Economic Forum, which took place from August 31 to September 1, 2022 in Saint-Malo. During these two days, the FEB met with all the players in the Breton economy. On the program: conferences, round tables and discussions on renewable energies and their economic impact.

Youth employment: meeting with Matthieu Garin

Youth employment: meeting with Matthieu Garin

Many players from all walks of life participate daily in the realization of the wind project in the Bay of Saint-Brieuc. Among them, we find in particular young graduates, who today tell us the secrets of their career and their arrival within the company Ailes Marines . Meeting with Matthieu Garin, Project Engineer.

Meeting with Gwennael Jezequel, Environment Manager

Meeting with Gwennael Jezequel, Environment Manager

Gwennael Jezequel has worked on the Saint-Brieuc project since 2018, as Environment Manager. Responsible, among other things, for piloting the continuous improvement of the environmental performance of the project, Gwennael Jezequel tells us about her journey and her motivations.

The “Mock-up project” in Esbjerg is finished!

The “Mock-up project” in Esbjerg is finished!

At the beginning of 2021, the Saint-Brieuc team launched the Mock-up project which was mounted on land in Esbjerg (Denmark) in the Siemens Gamesa Renewable Energy facilities. During these 4 months, the teams worked on building a full-scale replica of the connection between the transition piece and the lower section of the wind turbine tower (including wiring and internals).